Woodland Park Zoo Forest Trailhead Construction Updates
October 2024
Updates will be posted on a monthly basis and as needed to communicate upcoming activities and any associated impacts to surrounding streets, sidewalks, and pedestrian pathways.
Upcoming Construction Activity
- October 4th – November 1st: Construction of Pavilion L1 – L2 Exterior Structure will occur. There will be increased trucking on N 59th From 7:00am – 9:00am & 50th Street 9:00am – 3:30pm.
- November 1st – December 3rd: Pavilion L2 Mass Plywood Panel Placement will take place. There will be increased trucking on N 59th From 7:00am – 9:00am & 50th Street 9:00am – 3:30pm.
- December 3rd – January 6th: Pavilion L2 – Roof Structure construction will occur. There will be increased trucking on N 59th From 7:00am – 9:00am & 50th Street 9:00am – 3:30pm.
Questions or concerns? Contact us anytime.
Project Email Inbox: Zoo@Sellen.com
About the Project:
The new Forest Trailhead experience will build on Woodland Park Zoo’s global conservation work, motivate guests to act to conserve forest habitats, and feature vulnerable and endangered animals representing forests of the world, including tree kangaroos. Much-adored red pandas, colorful birds and fascinating reptiles and invertebrates will also make their home in the new forest. Click here to learn more about the project.
Sellen’s team is partnering with the Woodland Park Zoo and LMN Architects for the construction of the Forest Trailhead project, set to begin in May 2024.